Brenda asked 8 years ago
I have 5 integrations and would like all 5 to run in a specific order, without having to select each one. Isn't there a group function somewhere??
Answers
Best Answer
Chris answered 8 years ago
There is a Run Map task that you can add to any map that you want in order to chain them together. I would recommend putting the tasks on the map success task (or both the map success and map failure if you want the next one to run no matter what) so that each map calls the next after it completes.

If you are on the latest SC build, you should also check the option so that each map will show in its own tab in the map progress window so you get feedback on each run and can view the success/failure counts for each.